In Bickhardt Bau AG's more than 40-year corporate history, it is one of the largest earthwork sites of all: 5 million cubic metres of soil needed to be moved for the expansion of the airfield of Kassel-Calden into a regional airport. However, in contrast to the kilometre-long new motorway or ICE routes, the entire machine performance was concentrated on an area of 200 hectares. It has been very rare that people have seen such a huge number of these big machines in action in one and the same place so far. At the building site, 55 dumpers, 5 heavy goods vehicles which are usually employed in mining and 15 four-axle vehicles were constantly on the go to transport the soil from the loading points to the installation areas. At minute intervals, they were loaded by the scoops and buckets of the 15 large excavators and giant wheel loaders, with capacities of several cubic metres. With the help of GPS-control systems, 15 caterpillars and five graders ensured a precise installation, with accuracy down to the centimetre. 20 road rollers ensured an adequate soil compaction. Furthermore, several lime spreaders, road milling machines and water tank cars were in continuous operation to improve the soil in partial areas.
With regard to soil movement, 150 qualified employees ensured average daily outputs of 60,000 cubic metres. In the light of a tight timetable for the execution of work, this high labour input became necessary in order to ensure the construction of an even landing strip surface on former agricultural areas with a maximum height difference of almost 30 metres, over a three-kilometre long section.
The job task of Bickhardt Bau and its ARGE partner also comprised drainage and soil improvement work. In this process, 66,000 metres of vibro-replacement stone columns and 20,000 metres of shallow pits, trenches, several drainages and channel ducts with diameters of up to DN 1400 as well as six rainwater storage reservoirs were constructed.
Earthworks:
5,300,000 m3 of soil were detached, loaded, conveyed and installed
265,000 tonnes of anti-freeze protection were delivered and installed
800,000 m2 of formation level
Soil improvement:
2,900,000 m3 of soil improvement
33,000 m treated with vibro-replacement stone columns
700,00 m² of geotextile were delivered and laid
Drainage:
22,000 m of trenches and shallow pits
5 rainwater storage reservoirs
9,000 m of drainage pipes, diameter DN 160 – 250
79 drainage manholes, diameter DN 1000 – DN 2500
300 m reinforced concrete pipe channel
Landscaping:
1,220,000 m³ of topsoil work
1,100,000 m² of lawn seeding